LIVIO DELIVERS $1.77+ M COST SAVING IN 150 COTTAGES PROJECT IN TEXAS

Project Overview
Location: Springtown, Texas 76082
A client approached us to explore cost-effective yet high-quality construction options for their 150 Cottages Project (Each approx. 1-story, 1200 sq. ft. home). The developers’ bid using Traditional lumber was 10% higher than what he could achieve using LIVIO’s Multi-trade pre-assembled building system for rapid construction.

Key Efficiency Drivers with Livio

Framing Labor Reduced by 75%

  • Use of Livio’s pre-assembled, high-strength building system streamlined the erection process.

Foundation Savings of 20%

  • Livio’s lightweight structural load reduced foundation requirements, translating into significant material and labor savings.

Electrical & Plumbing (MEP) Efficiencies

  • Rough-in costs for electrical and plumbing saw savings of over 33-35%

Cut at least 50% Overall Construction timelines

  • Better schedule reliability and coordination due to offsite precision

Up to 23% Savings on Windows

  • Standardized pre-installed window shipped with panels saves both material & labor cost!

GC's Construction Hard-cost Comparison

DescriptionGC's Quote (Traditional Lumber)LIVIO’s Quote (Panelized System)TypeTime SavingsCost Savings
City Permits$5,550.00$5,550.000%0%
Sewer Tap Fee$4,000.00$4,000.000%0%
Warranty Fees$500.00$500.000%0%
3rd Party Inspections - Energy$350.00$350.000%0%
Architecture$2,900.00$2,900.000%0%
Architect Plan Design$300.00$300.000%0%
Blueprints$25.00$25.000%0%
Lot Stake with House Envelope Survey$130.00$130.000%0%
Form Board Survey$250.00$250.000%0%
Plot Plan$85.00$85.000%0%
Site Work/Rough Grading$485.00$485.000%0%
Dumpster & Ext Clean$1,350.00$750.00Indirect50%44%
Erosion/Temp Fencing$75.00$50.00Indirect50%33%
Temporary Electric$390.00$250.00Indirect50%36%
Temporary Water$280.00$200.00Indirect50%29%
Portable Toilet$70.83$50.00Indirect50%29%
Termite Protection$187.33$0.00Indirect100%100%
Concrete Turnkey$10,341.50$8,841.50Indirect10%15%
Frame - Material$15,993.75$16,000.00Direct0%0%
Framing Labor$9,006.25$2,251.00Direct75%75%
HVAC Rough In$4,500.00$3,000.00Direct50%33%
HVAC Final$4,000.00$3,000.00Direct50%25%
Plumbing Rough In$3,000.00$3,500.00Direct50%-17%
Plumbing Final$3,100.00$2,000.00Direct50%35%
Plumbing Fixtures$2,019.82$2,019.820%0%
Electrical Rough In$4,500.00$3,500.00Direct75%22%
Audio/Video/Security$500.00$500.000%0%
Electrical Final$3,000.00$2,000.00Direct75%33%
Light Fixtures$1,200.00$1,200.000%0%
Roof Turnkey$3,900.00$3,900.000%0%
Gutters and Downspouts$300.00$300.000%0%
Specialty Elevation Windows$275.00$275.000%0%
Windows$2,350.00$1,800.00Direct90%23%
Exterior Doors$900.00$500.0044%
Interior Doors$1,460.00$1,460.000%0%
Garage Doors$600.00$600.000%0%
Insulation$1,818.00$1,818.000%0%
Drywall$5,454.00$5,454.000%0%
Drywall Patches$490.86$490.860%0%
Vinyl/Laminate Installed$7,500.00$7,500.000%0%
Granite Counter Tops$2,500.00$2,500.000%0%
Cabinets$3,800.00$3,800.000%0%
Stair Parts$150.00$150.000%0%
Hardware$387.98$387.980%0%
Trim Labor$2,600.00$2,600.000%0%
Trim Materials$2,200.00$2,200.000%0%
Appliances$1,541.51$1,541.510%0%
Interior/Exterior Paint$5,403.75$5,403.750%0%
Mirrors$150.00$150.000%0%
Interior & Window Clean$300.00$300.000%0%
Power Wash Exterior$50.00$50.000%0%
Rental Equipment$500.00$750.00-50%
Unexpected Costs$500.00$500.000%0%
Project Management$3,902.00$1,951.00Indirect50%50%
Shipping (LIVIO Only)$9,647.00Direct
Total$118,013.27$106,167.6750% Faster~10% Savings

Conclusion

LIVIO’s proposal demonstrates how offsite construction can bring measurable savings, not just in labor, but in overall project cost and predictability. With a 10% reduction in hard costs across a 150-cottage development, the developer could save approximately $1.77 million, all while:

  • Reducing project risk
  • Streamlining scheduling
  • Minimizing labor dependency
  • Improving build quality

This case study sets a strong precedent for LIVIO’s role as a perfect solution for developers doing high-volume residential construction.